Earned Value Problem

Earned Value Problem

Earned Value Problems
Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.

1. During a project, Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000

B. CV: +100,000; SV: +120,000

C. CV: -100,000; SV: -120,000

D. CV: -120,000; SV: -100,000

2. You found the following Earned Value Analysis information for a recently closed out project:

SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.

B. The project’s deliverables have all been finished. The project came in ahead of schedule but on budget.

C. The project’s deliverables have all been finished. The project came in on schedule but over budget.

3.You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.
You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000.
What is right?
A. EAC = 550,000

B. EAC = 525,000

C. EAC = 500,000

D. EAC = 425,000

Students are often burdened with the task of writing essays. They need to master various academic topics, understand how to integrate facts and arguments, and organize all of this information in a clear and logical way. This is not an easy task for many students. But fear not! We’ve got your back. Here at MoreEssays.com, we offer professional academic help that can take on all these tasks on your behalf. All you need to do is fill out the Order form with your paper’s details, and we will get started on it right away!

Click Here to get this paper done within your deadline 

Can't find what you are looking for?

Post your question on MoreEssays.com and get help from one of our expert tutors in topics ranging from mathematics to rocket science!